Free up `bighp1` 40Gb ports
To link in the CloudLab2 Phase3, we need to free up some (10?) 40Gb ports on bighp1
.
The chosen strategy will be to convert the 4x40Gb control network LAGGs for the Moonshot ARM chassis to be 2x10Gb instead. Let us start here:
Card 0 (24 x 40Gb):
0/0/1-4 BAGG1 (ch4, ctrl)
0/0/5-6 BAGG21 (ch11, ctrl, part1)
0/0/7-10 BAGG2 (ch5, ctrl)
0/0/11-12 BAGG21 (ch11, ctrl, part2) [both DOWN -- unplugged?]
0/0/13-16 BAGG3 (ch6, ctrl)
0/0/17-18 BAGG22 (ch12, ctrl, part1)
0/0/19-22 BAGG4 (ch7, ctrl)
0/0/23-24 BAGG22 (ch12, ctrl, part2)
and free up ports 3/4, 9/10, 15/16, and 21/22. Note that these are likely to be a major PITA to get to physically, but at least it is the card on the end! I will work with @kwebb to get this done so that @amaricq can do the wiring.