Get the 32-port 100Gb Barefoot switch up and running
Brent wants to use this, so we need to get it integrated in the testbed and wired up to some nodes.
The short-term plan is to connect up 8 of the new c6525-100g nodes directly as they have a second, unused 100Gb port.
-
Rack the switch in V05 -
Wire up the nodes -
Apply a feature to the nodes so they can be specified in a profile (and possibly to dis-favor them for normal use) -
Add the switch to the DB and make the management interface accessible in a safe way Down the road: -
Ability to reload the switch OS
Edited by Mike Hibler