The Master Plan (tm) for moving to our new IP subnets:
* Mail users explaining downtime
X Mail users explaining downtime
* Fix hardcoded things in datbase/files (see Leigh's mail for list)
* Set up experimental simulation on test Cisco
X Set up experimental simulation on test Cisco
* Save configurations on ciscos 1 and 2
* Put Netcomm port in own VLAN, enable, set up routing in Cisco2
X Put Netcomm port in own VLAN, enable, set up routing in Cisco2
* Move plastic to new VLAN, change IP, route
X Move plastic to new VLAN, change IP, route
* Move paper to new VLAN, change IP, rotue
X Move paper to new VLAN, change IP, rotue
* Move control network ports to new VLAN, reboot testbed machines
***** IP addresses to change
* Paper's .214 interface becomes .128 - Fix local routing table
X Paper's .214 interface becomes .128 - Fix local routing table
* Plastic's .214 interface becomes .129 - Fix routing
X Plastic's .214 interface becomes .129 - Fix routing
* Cisco1's IP interface (becomes a .128)
......@@ -30,9 +30,11 @@ The Master Plan (tm) for moving to our new IP subnets:
* All testbed nodes become .132's (in dchp and proxydhcp config)
* Make changes permanent on paper/plastic
***** Misc things to do
* Set up the UDP helper port to forward from the control VLAN to
X Set up the UDP helper port to forward from the control VLAN to
* Get DNS records (forward and reverse) to agree with new setup
......@@ -45,21 +47,21 @@ The Master Plan (tm) for moving to our new IP subnets:
***** VLANs to create
* Outside: Consists only of cable running to outside router and a fake router interface
X Outside: Consists only of cable running to outside router and a fake router interface
* Private: Already exists as VLAN 666 - Add paper's interface (3/25) to this
X Private: Already exists as VLAN 666 - Add paper's interface (3/25) to this
(Power controllers are 4/30-44 (evens)) and cisco1 (4/23) and cisco4 (4/2)
* Public: For now, just plastic's interface (3/23) and router
X Public: For now, just plastic's interface (3/23) and router
* Control: All tbpcs (3/1-20,3/29-48), router, temporarily 214 net wire (4/27)
X Control: All tbpcs (3/1-20,3/29-48), router, temporarily 214 net wire (4/27)
***** Some kludges to get around potential problems
* Paper and plastic should be able to keep their .212 interfaces for an
indefine period of time
* Paper can get a .130 interface temporarily if the 'UDP helper' port (for
X Paper can get a .130 interface temporarily if the 'UDP helper' port (for
DHCP) is problematic
***** Simple IP allocation description
......@@ -71,3 +73,8 @@ The Master Plan (tm) for moving to our new IP subnets:
* Control (sharks): 155.101.130/24
* Control (PCs): 155.101.132/22
***** NOTE:
ip address 155.99.238.130 255.255.255.252
ip route 0.0.0.0 0.0.0.0 155.99.238.129